Is QuickBooks good for construction?

By Daniel Petrik, builder & founder of Firmabuilt · October 19, 2026 · 14 min read

QuickBooks is good for construction bookkeeping, and on its Plus and Advanced plans it can do job costing if every bill, receipt and timesheet is coded to that job. Its Advanced plan now lists construction budgets, job costing and change orders, and Intuit's own time app, sold separately, lets a crew clock in to a job from a phone.

Whether it's enough comes down to your plan and who does the coding. Each crew hour has to land on the right part of the job, picked by the worker at the clock or split up by the office later. This page is about QuickBooks Online, from Intuit's own pages. QuickBooks Desktop is a separate product, so check Intuit's pages for yours.

What QuickBooks does well

It keeps the books: the bills you owe, the checks and expenses you pay, the invoices you send. That's the record your bookkeeper and your CPA work from, and nothing on this page replaces it.

Intuit says QuickBooks Online Plus and Advanced include job costing too, which it defines as tracking all the costs of a job or project to work out how profitable it is. You set up a project under a customer, then pick that project in the Customer/Project field on each bill, check and expense that belongs to the job.

On a flip there's no client to pick, so some flippers enter the house, by its address, as the customer, and others enter their own company and make each house a project under it. That's a judgment, not a count; ask your bookkeeper how yours is set up.

Crew labor reaches the project one of two ways, Intuit's help says. Payroll costs, the wages plus costs like the payroll taxes you pay as the employer and workers' comp, post to the project after you run payroll. If your payroll isn't Intuit's, they post only after you enter them by hand, each time you run payroll. Or you type an estimated hourly cost for each employee: the wage and employer taxes, plus workers' comp or overhead if you add them. It shows on the project as soon as the hours are in, for hours tracked after you set it, but may be less exact. Intuit says choosing between the two changes what the project shows, not your books.

Both lean on timesheets tracked to that project. On Advanced, Intuit adds project estimates and a report of estimate against actuals.

What Advanced and Intuit's time app now cover

Advanced is the highest of the QuickBooks Online plans on Intuit's pricing page. Intuit also sells Intuit Enterprise Suite, which it describes as built for companies with several entities, as a separate product.

Intuit's August 2026 update says what it calls construction financials will now be included in Advanced: job costing, budget against actuals, AIA-style invoicing tied to phases and milestones, change orders and work-in-progress (WIP) reports. The same update says availability varies by product and not all features would be available on August 1. Intuit's help pages on phases and on projects, the projects one updated in October 2026, still describe phases for Advanced with a Construction add-on, so check what your subscription includes. On Intuit's pages, those features are:

  • Phases. The stages a project is broken into, each with a status and optional start and end dates. You can group the project's budget by phase and link expenses to a phase.
  • Purchase orders. On Plus and Advanced, a purchase order tells a vendor what you mean to buy; it reaches your books when you add it to a bill or expense. On Advanced with the construction features, a purchase order's lines can be put on a phase to track committed costs.
  • Change orders. Intuit describes them from the client's side: when a client approves one, the estimate, budget and invoice that go with it update automatically.

Intuit's time app is QuickBooks Time, in Premium and Elite versions. You can buy it to go with QuickBooks Online, and it comes with the Premium and Elite plans of Intuit's payroll, which Intuit now sells as QuickBooks Workforce. The phone app goes by QuickBooks Workforce too; it used to be the QuickBooks Time app.

A worker chooses a job or customer, selects Clock In, and switches jobs during the day. You decide which customers and projects each worker sees, you can show or hide service items for a given customer or project, and you can make a service item required on every timesheet. Intuit's reports total the hours by customer, project or service item.

On Intuit's pages, the app can also log where a worker is. The company turns this GPS tracking on or off for each worker and can make it required to track time. When it's on, the app logs the location at clock-in and updates it through the day, not only at the punch. Intuit says it stores no points on a break or off the clock, and employers never see off-the-clock points. Geofencing, "Available in QuickBooks Time Elite only," puts a boundary around a job site that reminds workers to clock in when they arrive and out when they leave. To do that the app checks the phone's location off the clock too; Intuit says those points stay on the phone.

So a crew can put its hours on a job from a phone, and on a part of the job if a service item goes on every entry too. On Intuit's pages that's a field filled in on each entry. The worker fills it at the clock, and if it's required and they skipped it, the app asks again at clock-out. It can also be filled by whoever clocks in a whole crew, or by the office when it enters or edits the time later. The office can also put the job on a scheduled shift that workers clock in to; Intuit's page on shifts lists custom fields on a shift but doesn't name service items.

How job costing works in QuickBooks

For QuickBooks to say what a job cost, and what each part of it cost, three things have to be coded:

  • Bills, checks and expenses: the project, on each one.
  • Crew hours, to the job: a customer or project on every time entry. Payroll then carries the wages and taxes to the project, or your estimated hourly cost does.
  • Crew hours, by part of the job: something on every entry that says kitchen or bath. One way is a service item for each scope, say "Kitchen labor" and "Bath labor". A service item is an entry on your QuickBooks products and services list, which Intuit describes as services you provide to customers, each with a rate and an income account. You pick one in the Service field of each time entry, beside the customer or project, to say what kind of work the hours were, and Intuit's reports can total hours by it. (A judgment: your bookkeeper may use another timesheet field.)

Say two of your crew spend a week on one house, across the kitchen and the bath, and you want QuickBooks to say what each scope's labor cost.

PersonMonTueWedThuFri
AKitchen 8Kitchen 8Kitchen 4, Bath 4Bath 8Bath 4, Kitchen 4
BBath 8Bath 4, Kitchen 4Kitchen 8Kitchen 4, Bath 4Bath 8
LineCount
Time entries, at the fewest: one per person, day and scope (a clock-out for lunch makes two)14
Fields each entry needs: a customer or project, and a service item for the scope14 × 2 = 28
Entries on split days, where only someone who was there knows when they switched8, on 4 days
Kitchen and bath hours, if every entry carries its service item40 and 40, 80 in all

Who codes it: the crew at the clock, if your time app shows that job's service items, or the office on Friday. On the eight split-day entries, only the worker, or a lead who was there, knows when they switched. Unless one of them wrote it down that day, on paper or a phone, the office coding them on Friday is guessing. (A judgment.)

Payroll sees 80 hours. Only the coding says 40 in the kitchen and 40 in the bath. To turn those hours into dollars, cost them at what an hour really costs you, not the wage: how to calculate labor burden works out that rate.

What it leaves to you

The split by scope: at the clock or on Friday

Intuit's time app can put crew hours on a job, and on a service item if the crew pick one at the clock; you can make that required. Otherwise the office codes the week later, from whatever the crew wrote down, and guesses on the split days where nobody did, as in the week above.

Either way, someone has to switch when the work switches. Forget at lunch and the whole afternoon lands on the morning's scope, on paper or on a phone. If the crew pick the service item at the clock, an app moves who records the split, from the office to the worker, and when, from Friday to the moment they switch. It doesn't make the split true.

Signed sub money before the bills

Your books see a sub's money when the bill comes in. What you've signed is committed from the day you sign it, paid or not. Say you sign the tile sub at $9,000 for the bath: that scope is $9,000 committed that day, still $9,000 after you pay his first bill, and moved only by an approved change order. Your books show none of it until he bills you or you pay him, unless you track it another way. On Advanced with the construction features, a purchase order's lines on a phase count as committed costs, if you enter them. How to budget a house flip explains signed against paid, and how to avoid cost overruns why an overrun can be locked in the day you sign.

Advanced's change orders, as Intuit describes them, are ones a client approves. A sub's signed price moves by a change order on your contract with him, whoever you build for, and on a flip, with no client, those are the change orders that move your cost. Ask your bookkeeper how your books carry one. If his contract is on a purchase order, the change needs entering there too, or the committed cost leaves it out.

The schedule

With the construction features, each of Advanced's phases can carry a start and end date and a status you set by hand: Pending, In Progress or Completed. Intuit says setting those deadlines and updating the statuses helps you spot delays early. If your job needs tasks that wait on each other, so that pushing the drywall moves the paint and the finish date, check whether your plan does that before you rely on it. The critical path method explains why that chain sets your finish.

When QuickBooks is enough

These are rules of thumb, not research. QuickBooks on its own will usually do if:

  • You sub everything out, and your bookkeeper codes each bill to its job. The sub's bill already says which scope it was.
  • Your crew already pick a job and a service item at the clock, at every switch, and someone checks it each week.
  • You're on Advanced with its budgets and change orders, you build for clients, and you actually use them.

The general question, for any tool, is whether you'd change a bid, an offer or a sub-versus-crew call on the number. The benefits of construction management software has that test, and the cases where you don't need software at all.

Running both: what goes where, and what you'll enter twice

A job tool beside QuickBooks doesn't replace the books, and some things get entered twice. Entered twice means a person types, codes or matches the same dollar or hour once in the job tool and again in your books or payroll. That's extra work, not the same cost booked twice in your books, which is a different problem, after the table. Say you run both:

The numberWhere it livesEntered twice?
Money in and out of the bankYour booksNo
A receipt's job and scopeCoded in the job tool. A download can include a column naming the job; whether it names the scope too depends on the toolYes: coded in the job tool, then matched or coded again in the books
A sub's bill, and the draw that pays itA bill in your books; a payment against the contract in the job toolYes
Crew hoursThe job tool, then a download to payroll, if your payroll takes a fileTyped again if your payroll doesn't take the file
Wages and payroll taxesPayroll, then your booksNo
Signed sub contracts, their change orders, the scheduleThe job toolNo, unless you also keep the contracts as purchase orders in your books

One more, as a judgment: if your books also pull in your bank's transactions, a purchase that comes in from the bank and again in an imported file is booked twice unless someone matches the two. The same goes for a sub you've paid: if your bookkeeper already entered the sub's bill and the imported file also carries the draw that paid it, the bill and the draw book the same cost twice. Ask your bookkeeper which path you use before anyone imports anything.

What adding a job tool costs

Start with the monthly bill. Then add the hours to set it up; the hours it takes every week to approve timecards, fix missed punches, code receipts, enter change orders and keep the schedule current; what gets entered twice, above; and the learning time. As a judgment, the first job on any new tool runs slower, so decide before you start what you'd need to see, and judge it on the second job. Then there's the crew, who have to clock in and switch every time, and may push back.

How much construction software costs adds up the money and the hours, how to get employees to clock in and out covers the crew, and the benefits page weighs it against what it changes. If you keep the job in a sheet today, Excel for construction project management starts from there.

Where Firmabuilt's job costing differs

The difference is where a crew hour lands. In Firmabuilt, a job is split into scopes, and the work is tasks, each set up with a trade and, when you give them, a scope and a cost code. On the Crew plan, a worker taps Clock in, picks the job and then the task, and taps Switch task when the work changes. When they clock out or switch, their paid hours post as a cost on that task's scope and cost code, at the hourly rate and burden multiplier you typed for that worker. Nobody on the crew picks a cost code or a service item. The scope and cost code come from the task, and a task can be saved without either: hours on a task with no scope still cost the job but count against no scope's estimate, and hours on a task with no cost code post with no code.

What that doesn't change: the worker still has to switch when the work switches. The cost works like Intuit's estimated hourly cost: the paid hours times a fixed rate for each worker, here your hourly rate times your burden multiplier. Firmabuilt doesn't work out your burden for you, and the multiplier starts at 1.0, which costs labor at the raw wage. It won't match what payroll paid: Firmabuilt doesn't work out overtime, so an overtime hour costs the job the same as any other.

When the work isn't on the list, the worker taps "Something else" and writes what it is, and the time goes to a holding task on the job. Until a manager or crew lead sorts it, that labor counts on the job but against no scope or cost code. Sorting puts it on a trade, under a task named for the work: an open task of that name if there is one, otherwise a new task with no scope or cost code, which leaves those hours unscoped and uncoded.

On every plan, each scope's budget shows Estimate, Committed and Actual. Committed is what you've signed for that scope with subs and suppliers, paid or not, approved change orders included, so a sub's change moves the scope the day it's approved. A signed contract's figure moves only by a change order, or by a correction you mark as a typo, and the contract's history keeps both. A scope signed past its estimate raises an alert as soon as it's signed. A contract file, or a purchase order in your books, holds the same signed figure; the difference is that here it sits on the scope beside what's spent, the day you sign.

Every contract in Firmabuilt is one you pay, with a sub or a supplier. A contract with your client, the client's change orders and what you bill them aren't in Firmabuilt; those stay in your books.

The schedule is built from the same tasks: you put a task on it and link it to the tasks it waits on, and pushing one moves what's linked after it. A wall calendar or, with the construction features, Advanced's phases hold dates too; what's different here is that the dates sit on the same tasks the hours cost to.

Receipts are coded too: each stays on the job it was handed in on, and the person coding it picks a cost code and, when the job has scopes, a scope. A receipt whose lines belong to different codes or scopes splits across them. One left as "General — not scoped" stays on the job but off every scope. QuickBooks puts a receipt on the project too; what's added here is the scope and cost code, and if you run both, the table above shows it's coded twice. How the task clock works goes through the details.

What it doesn't do beside your books: there's no live connection to QuickBooks, so nothing moves between the two on its own. You download a CSV, a plain file of rows and columns that any spreadsheet opens. It's a copy as of the day you download it, so a change you make in Firmabuilt afterwards doesn't reach the file or your books. Getting its rows into QuickBooks is up to whoever keeps your books.

The spending download has a column headed Customer:Job, set to the job's property address, plus cost code, trade and task. Customer:Job is Firmabuilt's own heading. In QuickBooks Online the field is called Customer/Project, and a project there carries whatever name you gave it, which may not be the address. There's no scope column, so the split by scope stays in Firmabuilt. In-house labor is left out unless you tick it: "Off by default. If payroll already posts wages to your books, including them here books the same labor twice."

On the Crew plan, the hours download for payroll has one row per person, day, job, trade and task, in paid hours, again with no scope column. Hours nobody has approved yet are in it, marked no in its Approved column, and "Overtime is deliberately not calculated": your payroll works that out. Neither file has been checked against a live QuickBooks or payroll import, so have your bookkeeper try one week's file first.

Firmabuilt doesn't run payroll, pay anyone or file anything, and it doesn't keep your books, invoice a client or collect signatures: contracts and change orders are signed wherever you sign them now, and Firmabuilt records the figure. It's job cost beside your books, not instead of them.

Questions

Can QuickBooks do job costing?

Yes, on QuickBooks Online Plus and Advanced, for whatever is coded to the job. Bills, checks and expenses carry the project you pick on each one. Crew labor reaches the project through timesheets tracked to it, either as payroll costs after you run payroll or as an estimated hourly cost straight away. Advanced adds project estimates and a report of estimate against actuals. Splitting a job's labor by scope takes one more field on every time entry, such as a service item.

Does QuickBooks have project management?

It has projects, which on Plus and Advanced group one customer's transactions and track a job's income and costs. Advanced adds estimates against actuals, and with its construction features, phases with optional start and end dates and a status, a budget by phase, purchase-order lines put on a phase to track committed costs, and change orders your client approves. Intuit's August 2026 update calls its construction features construction financials. If you need tasks that wait on each other, check what your plan does before you rely on it.

Can QuickBooks track crew hours by job?

Yes, with QuickBooks Time, Intuit's time app, in Premium and Elite versions. You can buy it to go with QuickBooks Online, and it comes with the Premium and Elite plans of Intuit's payroll, QuickBooks Workforce. A worker picks a job or customer on the phone app, clocks in, and switches jobs during the day. Hours land on a part of the job when a service item, or another timesheet field, is picked too, by the worker at the clock or the office later; you can make a service item required on every timesheet. Intuit says geofencing is in Elite only.

Do I need construction software if I have QuickBooks?

Only if knowing what each scope really cost would change a bid, an offer or a sub-versus-crew call, and you can't get that number from your books with the coding you'll actually keep up. The benefits of construction management software has a test to run on your last job.

Does Firmabuilt connect to QuickBooks?

Not directly: there's no live connection. You download CSVs: spending, with a Customer:Job column set to the job's property address, and, if your crew clock in, their hours for payroll. Neither file has been checked against a live QuickBooks or payroll import yet, so try one week's file with your bookkeeper before you rely on it.

Job cost beside your books, not instead of them

Firmabuilt keeps the job: scopes, signed contracts, change orders and the schedule. On the Crew plan, the crew clock in on the task and the hours land on its scope. Spending downloads as a CSV with a Customer:Job column, and on the Crew plan, so do the crew's hours, for payroll.