To stay organized as a contractor, keep five records for every job, and write in them the day things happen: what you priced and what you've signed, what you've spent, who worked on what, what's next, and what changed. A notebook, a spreadsheet or an app can hold them. What matters is that each one has a single home, and that the money in it adds up when you total it.
Below: what goes in each record, which ones federal law already asks you to keep and for how long, a paper system that holds up, and the signs it's running out.
The five records every job needs
One record for each question a job keeps asking: what will it cost, what has it cost, who did the work, what happens next, and what changed since you priced it. A scope, below, is a piece of the job you price as one: the kitchen, the roof, the hall bath.
| Record | What goes in it | Write it | More on it |
|---|---|---|---|
| The budget: what you priced and what you've signed | Each scope's estimate, and beside it every contract you've signed and every order you've placed for that scope, with their approved change orders | The estimate before you commit to the job; each signed line the day you sign | A flip budget; avoiding overruns |
| What you've spent | Every receipt and paid bill, marked with its job and scope. Your own crew isn't paid by bill: their cost is the hours in the next record, at what an hour costs you | The day you buy or pay | The paper system, below |
| Who worked on what | Each person, each day: the hours, and the scope they were on | That day, by someone who saw the work | What an hour costs; getting the crew to clock in |
| What's next | The order of the work, the dates, and what each step waits on: a trade, a delivery, an inspection | Whenever a date moves | The order to renovate in; the critical path |
| What changed | Every change to a signed price or scope: the date, the contract, plus or minus, the reason, who approved it | Before the work | Change orders |
What you've signed is the whole amount you've agreed to pay for a scope: every contract you've signed and every order you've placed for it, with their approved change orders, paid or not. In a budget it's usually called committed, though some reports use committed for only the part you haven't paid yet. It sits beside the estimate because an overrun can happen the day you sign, long before the last bill arrives.
Some things are left off the list on purpose. Lien waivers, insurance certificates and warranties are papers you collect and file, not records you write in: give them a folder per job. Permits and inspections go on the schedule, as dates the next step waits on, and a copy of the permit and each inspection's result go in that folder. And the money coming in, a client's payments, a lender's draws or a flip's sale, goes through your books with your bank deposits. These five are what the job costs and when it gets done.
Start with the records you already have to keep
At least two of the five overlap with what the law already asks for: receipts and paid bills back up your tax return, and your hourly crew's daily hours are part of their payroll record. What follows is federal law only. It's general information, not legal or tax advice. State law can require more, so ask your CPA or an employment attorney.
What the IRS asks for
Mostly, no particular kind of record. IRS Publication 583 says it plainly: "Except in a few cases, the law does not require any specific kind of records." You can use any system that clearly shows your income and expenses, backed by the papers behind each entry, which the IRS says include sales slips, paid bills, invoices, receipts, deposit slips and canceled checks.
Two areas with rules of their own come up for builders. If you deduct the cost of driving for business, IRS Publication 463 asks for a record that includes the miles, date, destination and business purpose of each business trip, plus your total miles for the year. Keep it as you go; a weekly log counts. And if you have employees, there are specific employment tax records you must keep, which IRS Publication 15 lists.
Paper is allowed, and so is an app. The same rules apply to records kept electronically, and if you keep them on a computer you have to be able to produce legible records that back up your return. That goes for a photo of a receipt too: the IRS lets you throw the paper away only once you've tested that the copies are complete and readable and that you can find each one again, and you keep it that way. So whatever holds your records, a box or an app, has to give them back years from now. Before you trust any app with them, find out how you get them out.
How long to keep them
| Records | How long, under federal rules |
|---|---|
| Tax records, generally | 3 years after you file the return they support, counted from its due date if you filed early |
| Employment tax records | At least 4 years after the tax becomes due or is paid, whichever is later |
| Payroll records for hourly workers | At least 3 years from the last entry |
| Time cards with each day's start and stop times | At least 2 years from the last entry |
| If you left off income of more than 25% of the gross income your return shows | 6 years |
| If you claim a loss on worthless securities or a bad-debt deduction | 7 years |
| If you didn't file a return, or filed a fraudulent one | Indefinitely |
| Records on property | Until the limitations period runs out for the year you sell or otherwise dispose of it |
The 6 and 7 years also count from the due date if you filed early. When a record falls under more than one line, keep it for the longest: the wages and pay dates in a payroll record are employment tax records too, so keep them 4 years, not 3. How a flip is taxed is a question for your CPA, and so is which of these lines its records fall under.
The Small Business Administration adds that closing the business doesn't end this: you may still be legally required to keep tax and employment records, and common guidelines advise keeping records for anywhere from three to seven years. That range is advice, not law. The federal rules above still apply after you close, and some of them run longer.
What federal wage law asks for
If your hourly workers are covered by federal wage law, you have to keep a payroll record for each of them, and one thing it has to show is the hours worked each workday and the total for each workweek (29 CFR 516.2(a)(7)). The same record holds, among other things, when their workweek starts, their pay rate, overtime pay, deductions, the wages paid each pay period and the date they were paid. Wage law says to keep payroll records at least three years and the time cards behind them at least two, safe and where you can get at them: where the work is, or at your office, as long as you can make them available within 72 hours of the Labor Department asking. The wages and pay dates in them are also employment tax records, so keep those four years, as above.
The Department of Labor leaves the method to you: "Employers may use any timekeeping method they choose." Its own examples are a time clock, someone who keeps track of everyone's hours, and workers writing down their own times. Whichever you pick, it counts as long as it's complete and accurate.
Covered has a definition. Federal wage law covers the employees of a business with at least two employees and at least $500,000 a year in sales or business done. Below that, a worker is still covered on their own if their work regularly involves commerce between states. Most construction employers' hourly workers are covered one way or the other, but that's a judgment, not a ruling: if you're not sure, check with the Department of Labor or an employment attorney.
The law asks for records, not software. And nothing in the federal hours rule asks which job the hours went to. That part is for you: it's what turns a payroll record into each job's labor cost. Your CPA may need it too: on a house you own, like a flip, the IRS says the wages you pay your own employees to build or improve it go into its basis instead of being deducted. Public jobs paid at prevailing wage have record rules of their own, which this page doesn't cover.
A paper system that holds up
This is one way to set it up, not the only one. It's a judgment, built so each record has one home and gets written the day it happens.
- One book, with a page per job per day. Who was there, each person's hours and the scope they were on (two lines if they moved), what got done, and what's in the way. The Department of Labor's own examples include someone who keeps track of everyone's hours and workers writing down their own times, so a lead can keep the lines, or each worker can write their own.
- Two pages at the front for each job. The budget: each scope's estimate, and under it every contract you sign and every order you place for that scope, written in the day you sign or place it. And the schedule: the order of the work, the dates, and what each step waits on, permits and inspections included.
- An envelope per job for receipts, filed the day you buy. Write the scope on each receipt before it goes in. A receipt that rides in the truck for three weeks leaves its scope short for three weeks.
- A change sheet, signed before the work. The date, the contract, plus or minus, the reason, and both signatures. Copy the new figure onto the budget page the same day. What a change order is has the full list of what goes on one.
- A Friday sit-down. For each scope, total what you priced, what you've signed and what you've spent. Check that the week's hours in the book add up to the hours payroll paid; if they don't, a line is missing somewhere. Then move the dates that slipped.
How much it has to hold
Say you count what has to be written down in a week. A line is one person, one day, one scope: that person's hours on that scope that day, the same unit the spreadsheet page uses. Say each person makes seven lines a week: three days each spent on a single scope, one line apiece, and two days each split between two scopes, two lines apiece, so 3 + 2 × 2 = 7.
| Entry | One job, 3 crew | Three jobs, 8 crew |
|---|---|---|
| Crew lines, 7 a person | 3 × 7 = 21 | 8 × 7 = 56 |
| Receipts (say) | 6 | 15 |
| Changes (say) | 1 | 2 |
| Entries a week | 21 + 6 + 1 = 28 | 56 + 15 + 2 = 73 |
| Per working day (5 a week) | 28 ÷ 5 = 5.6 | 73 ÷ 5 = 14.6 |
Contracts signed and dates moved come on top. Even so, either column fits in a notebook written the same day: about six entries a day, or about fifteen. Writing isn't the hard part; having seen the work is. The crew lines are the ones that go wrong, because whoever writes them on Friday usually wasn't there when someone moved from the kitchen to the bath. That's a judgment, and Excel for construction project management works through what a wrong split costs.
When paper is enough, and when it runs out
Paper is doing its job while it's written the same day, by someone who saw the work, and the Friday totals add up. These are signs it's running out. They're rules of thumb, not findings from any study:
- Entries get written from memory a day or more later.
- The book is in one truck, and the numbers are needed somewhere else.
- The Friday sit-down runs past an hour.
- Whoever writes down which scope the hours went to wasn't there to see it.
- The Friday totals don't add up, week after week.
If none of those is true, keep the notebook. If one is, the next step doesn't have to be software. A spreadsheet holds the same five records, does the totals for you, and a shared copy isn't stuck in one truck. It doesn't get anything written the day it happens, or by someone who saw the work: that part is still a habit. Whether software is worth it at all, and a test to run on your last job before you decide, are in the benefits of construction management software.
Moving to software costs something too: the monthly bill and the hours each week it takes to keep up (what construction software costs adds both up), the hours to set it up, the time it takes to learn, and a crew that has to change habits (getting employees to clock in deals with that). Paper has a weekly cost of its own: the Friday sit-down. One judgment, not a finding: the first job on any new tool runs slower, so if you switch, decide before you start what you'd need to see, and judge it on the second job.
The five records in Firmabuilt
Firmabuilt keeps four of the five on every plan. The budget shows each scope's Estimate, Committed and Actual, and on the scope page Committed carries the hint "Signed contracts". A receipt is coded to its job, its lines split by scope and cost code, with the tax spread so they add up to exactly what was paid. A signed contract's figure moves only by change order or a marked correction, and every other edit leaves a line in its history. The signatures stay on the paper. The schedule holds what's next: a phase can carry a gate date, and once it's locked nothing in that phase is scheduled before it, which is where an inspection or a permit goes.
Who worked on what takes the Crew plan: the crew clock in on a task, and each shift's cost posts to that task's scope. A crew member can also mark a task blocked as "Failed or waiting on inspection". Each job's Daily log lists, by day, the shifts worked, the problems reported, the photos taken and, for whoever can see the job's money, what was spent, so on the Crew plan the day's hours fill themselves in from the clock. The clock moves who records the split. It doesn't make the split true: someone still has to switch tasks when the work switches.
It has nothing built for lien waivers or insurance certificates. It doesn't run payroll or file anything, and its timecards hold the hours your crew clock, not your whole payroll record: it doesn't work out overtime, and it doesn't keep deductions, the wages actually paid or the pay date. On its Exports page, in a browser, spending downloads as a CSV file, and on the Crew plan so do the crew's hours. Receipt and photo files aren't in those downloads, so save the ones you need yourself. If a plan ends, the records are kept, and you can still sign in and open them.
Questions
What records does a contractor have to keep?
Under federal tax law, records that back up the income and expenses on your return. Except in a few cases, no specific kind is required, as long as your system clearly shows your income and expenses, backed by papers that the IRS says include sales slips, paid bills, invoices, receipts, deposit slips and canceled checks. With employees, add your employment tax records and a Form I-9 for each person you hire. If your hourly workers are covered by federal wage law, you also keep a payroll record for each of them, including the hours worked each workday and the total for each workweek. None of it has to be kept in software, and the federal hours rule doesn't ask which job the hours went to. Two cases do tie labor to a job: on a public job paid at federal prevailing wage, the payroll record shows the hours on each covered contract, and on a house you own, like a flip, the wages you pay to build or improve it become part of its cost, so ask your CPA how to carry them. This is general information, not legal or tax advice. Other federal rules and state law can require more, so ask your CPA or an employment attorney.
How long should a contractor keep records?
Under federal rules: tax records generally 3 years after you file the return they support (counted from its due date if you filed early); employment tax records at least 4 years after the tax becomes due or is paid, whichever is later; and if your hourly workers are covered by federal wage law, their payroll records at least 3 years and their time cards at least 2, each from the last entry. Some cases run longer: 6 years if you left off income of more than 25% of the gross income your return shows, 7 for a worthless-securities or bad-debt claim, indefinitely if you didn't file or filed a fraudulent return, and records on property until the limitations period runs out for the year you sell or otherwise dispose of it. A record under more than one line is kept for the longest: the wages you paid are both payroll and employment tax records. Your insurance company or creditors may want records kept longer than the IRS does. How a flip is taxed, and which of these lines its records fall under, is a question for your CPA. This is general information, not legal or tax advice. State law can require more, so ask your CPA or an employment attorney.
Is a notebook enough to run a construction business?
Yes, if it's written the same day and the money in it adds up when you total it. When it stops being enough, and what software would change, is in the benefits of construction management software, and when you don't need it.
How do you keep track of several jobs at once?
Give each job its own pages, so nothing from one lands on another, and total them all at one sit-down a week, in the same order every time. Or move them into a spreadsheet or an app that keeps the jobs apart for you. Which one fits depends on how many jobs and people you have, and on who writes things down. There's a test to run on your last job in the benefits of construction management software.